Your expected production now follows your grid transmission limit

Expected production, and the maximum you could reach under a clear sky, no longer rises above the "Grid Transmission Limit" you set for a plant. A grid operator's percentage setpoint is now measured against that limit instead of your inverters' combined peak. Figures already issued keep their values. Your plants receive this with their next agent update.

  • On plants whose grid connection is smaller than their inverter peak, expected production falls and lost energy during curtailment changes.
  • Plants without that limit keep the inverter peak as their reference and see no change.