FixMajorAgentProduction & yield
Expected production no longer exceeds the grid transmission limit
Expected production, and the maximum under a clear sky, no longer rise above a plant's "Grid Transmission Limit". A grid operator's percentage setpoint now counts against that limit, not the inverters' combined peak. Plants receive this with their next agent update.
- Where the grid connection is smaller than the inverter peak, expected production falls and curtailment losses change.
- Plants without that limit keep the inverter peak as their reference and see no change.
Shipped withmirox-agents 3.1.112