Changelog
Every change to Mirox, grouped by month. Filter by group or by kind of change.
November 20261
October 20262
Dashboard KPI counters now show the same figure on every device
The dashboard's KPI counters no longer differ between the web app and the Mirox app or leave a stale figure after a timezone, period or filter change. Figures already issued keep their value.
Revenue figures now use each plant's tariffs and contracts
Revenue on the dashboard and the revenue page is now valued with each plant's tariffs, contracts and fees instead of a flat rate. The running month shows a price, and each figure reads "Final", "Provisional", "Estimated" or "Not calculated".
September 20261
July's curtailment settlement now uses the official price
The readiness timeline's official-price row no longer shows July as overdue. July's settlement now uses the official price, and issued figures keep their value.
August 20266
Marktprämie figures per band are corrected and show their energy
The revenue tables now show an "Energy (§ 51 applied)" column: the energy each band's Marktprämie is actually paid on. Each band's premium is now worked out from that energy instead of being shared across the bands by capacity.
The revenue comparison now comes from the monthly settlement
The comparison of settlement methods on the revenue page now uses the figures from the monthly settlement. A month that has not been settled yet reads as unavailable instead of showing a number.
Curtailment excluded by § 51 no longer shows a euro amount
A quarter-hour excluded from remuneration by § 51 EEG no longer shows a euro amount. The amount disappears when the month is recalculated, while the excluded energy stays in kWh.
Curtailment compensation is no longer shown before 23 December 2025
Compensation for curtailed energy is now shown only for quarter-hours from 23 December 2025 on, the day that rule took effect. A compensation figure for a delivery month lying wholly before that date disappears the next time that month is settled.
Compensation no longer counts a curtailed quarter-hour twice
Where two sources sent readings for the same minutes — after a restart, for example — a plant's curtailed energy for that quarter-hour was counted twice, and the compensation shown read too high. Such a quarter-hour is now left out of the settlement, and figures already issued keep their value.
Curtailment compensation now follows the official published value
Compensation for curtailed energy is now priced against the official published value. Until that value is published, about two months after the delivery month, the figure stays an estimate and is corrected later.
July 20262
Revenue figures now follow each EEG rate and the marketer fee
A separate market premium is now shown for each EEG rate at a plant, counted only for the share of capacity that rate covers, and a marketer fee now lowers revenue. A plant with capacity outside the EEG shows less than before, and figures already issued keep their value until the period is recalculated.