AgentFixMajorRevenue & market

Declared outages now reduce the flat-rate curtailment settlement

The plant's outage register is now reported to the direct marketer, and declared maintenance or administrative outages reduce the flat-rate curtailment settlement. Compensation for a period with a declared outage goes down, and figures already issued keep their value. Plants receive this with their next agent update.

mirox 2.15.614 – 2.15.618mirox-agents 3.2.144
Web appFixMajorRevenue & market

Revenue figures now use each plant's tariffs and contracts

Revenue on the dashboard and the revenue page is now valued with each plant's tariffs, contracts and fees instead of a flat rate. The running month shows a price, and each figure reads "Final", "Provisional", "Estimated" or "Not calculated".

mirox 2.15.593 – 2.15.594

September 20261

August 20266

Web appFixMajorRevenue & market

Marktprämie figures per band are corrected and show their energy

The revenue tables now show an "Energy (§ 51 applied)" column: the energy each band's Marktprämie is actually paid on. Each band's premium is now worked out from that energy instead of being shared across the bands by capacity.

mirox 2.15.330 – 2.15.339
Web appFixMajorRevenue & market

The revenue comparison now comes from the monthly settlement

The comparison of settlement methods on the revenue page now uses the figures from the monthly settlement. A month that has not been settled yet reads as unavailable instead of showing a number.

mirox 2.15.310 – 2.15.329
Web appFixMajorRevenue & market

Curtailment excluded by § 51 no longer shows a euro amount

A quarter-hour excluded from remuneration by § 51 EEG no longer shows a euro amount. The amount disappears when the month is recalculated, while the excluded energy stays in kWh.

mirox 2.15.296 – 2.15.309
Web appFixMajorRevenue & market

Curtailment compensation is no longer shown before 23 December 2025

Compensation for curtailed energy is now shown only for quarter-hours from 23 December 2025 on, the day that rule took effect. A compensation figure for a delivery month lying wholly before that date disappears the next time that month is settled.

mirox 2.15.261 – 2.15.273
Web appFixMajorRevenue & market

Compensation no longer counts a curtailed quarter-hour twice

Where two sources sent readings for the same minutes — after a restart, for example — a plant's curtailed energy for that quarter-hour was counted twice, and the compensation shown read too high. Such a quarter-hour is now left out of the settlement, and figures already issued keep their value.

mirox 2.15.190 – 2.15.197

July 20263

Web appFixMajorRevenue & market

Revenue figures now follow each EEG rate and the marketer fee

A separate market premium is now shown for each EEG rate at a plant, counted only for the share of capacity that rate covers, and a marketer fee now lowers revenue. A plant with capacity outside the EEG shows less than before, and figures already issued keep their value until the period is recalculated.