November 20262

October 20265

Web appFeatureMajorRevenue & market

The assistant now estimates a plant's lost energy and its value

The assistant now estimates the energy a plant lost over a stated window, such as an outage, and its value per month at the plant's EEG value or market value, or a marked flat rate. For plants in the German market, the estimate carries a euro figure.

mirox 2.15.627 – 2.15.631
Web appFeatureMajorRevenue & market

A "Subscription" page now replaces the organization's "Contract" tab

The framework contract is now signed on the "Subscription" page, which replaces the "Contract" tab and the former subscription page. It shows the company that pays for each plant part, payment bundles, the subscription term, and the contract state.

mirox 2.15.622 – 2.15.659
Web appFeatureMajorRevenue & market

Reports now show expected revenue and a financial performance ratio

In reports, exports and the assistant, revenue now shows beside "Expected revenue" — the yield report's planned feed-in at the plant's EEG tariff, aged by module degradation — and a "Financial performance ratio", actual revenue divided by expected. A running month's expected revenue stops at the current moment, in reports, exports and the assistant.

mirox 2.15.595 – 2.15.596
Web appFixMajorRevenue & market

Revenue figures now use each plant's tariffs and contracts

Revenue on the dashboard and the revenue page is now valued with each plant's tariffs, contracts and fees instead of a flat rate. The running month shows a price, and each figure reads "Final", "Provisional", "Estimated" or "Not calculated".

mirox 2.15.593 – 2.15.594

September 20262

Web appFeatureMajorRevenue & market

A wind plant's curtailment settlement method can now be chosen

On a wind plant's "Market" tab, "Settlement method" now offers "Spitz Wind (power curve)", "Spitz Wind light (reference wind speed)" and "Pauschal Wind (flat rate)". Curtailed energy and its compensation are settled turbine by turbine against each turbine's certified power curve, and the plant figure is their sum.

mirox 2.15.494 – 2.15.496
Read more in the documentationMarketWindComponents

August 20268

Web appFixMajorRevenue & market

Marktprämie figures per band are corrected and show their energy

The revenue tables now show an "Energy (§ 51 applied)" column: the energy each band's Marktprämie is actually paid on. Each band's premium is now worked out from that energy instead of being shared across the bands by capacity.

mirox 2.15.330 – 2.15.339
Web appBreaking changeMajorRevenue & market

PPA contracts can no longer be settled on Mischpreis

Mischpreis can no longer be chosen under a contract's "Revenue model". A contract still set to it is valued at "Marktwert (as-if-produced)", and compensation for curtailment ordered by the marketer follows that model from this release, while figures already issued keep their value.

Action required: Plant and portfolio managers: open the market configuration of every plant whose direct-marketing contract was settled on the Mischpreis model, and confirm that "Marktwert (as-if-produced)" or "Fixed value" is the right revenue model for that contract. Marketer-curtailment compensation is calculated on the chosen model from this release; support helps you with an affected contract.

mirox 2.15.310 – 2.15.329
Web appFixMajorRevenue & market

The revenue comparison now comes from the monthly settlement

The comparison of settlement methods on the revenue page now uses the figures from the monthly settlement. A month that has not been settled yet reads as unavailable instead of showing a number.

mirox 2.15.310 – 2.15.329
Web appFixMajorRevenue & market

Curtailment excluded by § 51 no longer shows a euro amount

A quarter-hour excluded from remuneration by § 51 EEG no longer shows a euro amount. The amount disappears when the month is recalculated, while the excluded energy stays in kWh.

mirox 2.15.296 – 2.15.309
Web appFixMajorRevenue & market

Curtailment compensation is no longer shown before 23 December 2025

Compensation for curtailed energy is now shown only for quarter-hours from 23 December 2025 on, the day that rule took effect. A compensation figure for a delivery month lying wholly before that date disappears the next time that month is settled.

mirox 2.15.261 – 2.15.273
Web appFeatureMajorRevenue & market

The assistant now answers what a plant earned against plan

The assistant now answers what a plant earned in a month or a year: production revenue, the compensation for grid and marketer curtailment, and the market value behind them. Several plants are compared side by side and against the yield the plan expected, and months not yet settled are named as provisional.

mirox 2.15.228 – 2.15.234
Web appFixMajorRevenue & market

Compensation no longer counts a curtailed quarter-hour twice

Where two sources sent readings for the same minutes — after a restart, for example — a plant's curtailed energy for that quarter-hour was counted twice, and the compensation shown read too high. Such a quarter-hour is now left out of the settlement, and figures already issued keep their value.

mirox 2.15.190 – 2.15.197

July 20263

June 20262

May 20262