AgentFixProduction & yield

The performance ratio now comes from the inverters' own output

Wherever every inverter a plant expects has reported, the performance ratio now comes from what those inverters produced, not from the feed-in meter. Losses in the meter and the lines no longer count against it. Plants receive this with their next agent update.

mirox 2.15.376 – 2.15.393mirox-agents 3.1.435 – 3.1.442
AgentImprovements and fixesAlerts & events

Solar plants no longer raise an alert every night that a device stopped sending. A curtailed inverter no longer reads as an outage.

  • Inverters going quiet after dark no longer raise an alert at a solar plant, while a device that cannot be reached still alarms.
  • An inverter held down to zero by the direct marketer no longer counts as an outage while its own status says it is limited.
  • Huawei 33KTL-A and 36KTL inverters now show their real operating status and model instead of a wrong status code and their firmware.
  • Inverters are no longer flagged as measuring wrongly when one stray reading invents energy on a quiet string.
mirox-agents 3.1.435 – 3.1.442
Read more in the documentationInverter status codes
AgentFixProduction & yield

A failed grid meter no longer hides curtailed minutes

The performance ratio is no longer flattered at a plant whose grid meter cannot be reached. Minutes the plant spent held down at the grid operator's limit are now left out, even without a reading from that meter, instead of counting as clean production. Plants receive this with their next agent update.

mirox-agents 3.1.422 – 3.1.433
AgentImprovements and fixesAlerts & events

Reduced-output flags open and clear on firmer ground, and device-reported faults confirm and update during the day.

  • The "Reduced output" flag no longer stays on a recovered component.
  • A device-reported thermal or insulation fault now confirms its event within 15 minutes, and a changed alarm count appears on the event within 30 minutes.
  • A string behind a data logger now reports its negative current when it back-feeds.
  • That quarter-hour's feed-in energy no longer drops from the Marktprämie after a restart inside a quarter-hour.
mirox-agents 3.1.422 – 3.1.433
AgentFeatureMajorData collection

Huawei battery storage is now read down to its cells

A Huawei SmartLogger with a LUNA2000 battery behind it now reports the whole storage: its converters, the container, its racks, packs and cells, with power, charge and discharge limits, state of charge and cell state of health. Plants receive this with their next agent update.

mirox-agents 3.1.416 – 3.1.417mirox 2.15.361 – 2.15.366
AgentFeatureAlerts & events

Battery alarms now appear in a plant's event list

Alarms that NR Electric converters and Linyang battery containers raise about themselves now appear in the plant's event list, and an alarm closes again as soon as the device clears it. Each alarm shows how serious it is, and a Linyang alarm names the racks affected. Plants receive this with their next agent update.

mirox-agents 3.1.416 – 3.1.417mirox 2.15.361 – 2.15.366
AgentImprovements and fixesCurtailment & grid limits

Phoenix Contact Power Control Unit 4.0 controllers now report their limits, and a curtailed plant no longer raises underperformance alerts.

  • A Phoenix Contact Power Control Unit 4.0 now reports the grid operator's and direct marketer's limits and the setpoints given to the battery.
  • Inverters at a plant held down by the grid operator or the direct marketer are no longer reported as producing far below expectation.
  • A day on which half of a plant's components fall below expectation no longer raises an underperformance event on each of them.
  • A Phoenix Contact controller whose web interface has no login can now be added without one.
mirox-agents 3.1.416 – 3.1.417mirox 2.15.361 – 2.15.366
Read more in the documentationData loggers
AgentFeatureMajorData collection

Phoenix Contact AXL controllers can now be added as data loggers

A Phoenix Contact AXL controller can now be added as a data logger, reading every combiner box and string, the grid meter with its lifetime feed-in reading, and the irradiation and temperature sensors every 60 seconds. Plants receive this with their next agent update.

mirox 2.15.340 – 2.15.352mirox-agents 3.1.403 – 3.1.412
Read more in the documentationData loggers
AgentFeatureData collection

An Elsist DLMS concentrator can now be added as a data logger

An Elsist SlimLine DLMS concentrator can now be added as a data logger, reading a Landis+Gyr feed-in meter through it: grid power plus the lifetime feed-in and consumption counters, at the meter's own resolution. Plants receive this with their next agent update.

mirox 2.15.340 – 2.15.352mirox-agents 3.1.403 – 3.1.412
Read more in the documentationData loggers
AgentImprovements and fixesData collection

Production curves for each component now follow the day in 15-minute steps instead of filling in hour by hour. Curtailment figures now appear for plants that previously had none.

  • Curtailment figures now appear for plants without irradiation data and for five plants whose nameplate power could not be read.
  • An inverter now reports its active-power setpoint.
  • An outage on a dead inverter no longer closes and re-opens through the morning.
  • A component producing far below expectation no longer reads healthy after a stretch where it sent nothing.
  • Voltages from a data logger now read as phase-to-neutral under the new phase names.
mirox-agents 3.1.361 – 3.1.373
AgentImprovements and fixesData collection

A device's web page that answers only over HTTPS opens again. It is no longer noted as plain HTTP.

  • A device's web page that answers only over HTTPS is no longer noted as plain HTTP.
  • A device just found in a scan now opens its web page at once.
  • Curtailment episodes on a plant's "Activity" page show their current status again after the month's settlement has run.
mirox-agents 3.1.346 – 3.1.349mirox 2.15.274 – 2.15.278
Read more in the documentationNetwork devices
AgentImprovements and fixesAlerts & events

The plant analysis no longer writes off strings or inverters on the strength of a day when the plant was dark or partly out.

  • Strings are no longer marked as not connected after a day the plant was dark or hardly reporting.
  • A string marked that way earlier clears itself once it measures again, instead of waiting to be cleared by hand.
  • An inverter that was out for part of the day is no longer reported as producing far below what is expected of it.
  • An event closed on an inverter no longer re-opens by itself on a day that inverter recovered.
  • Configured strings that have never produced now count in the expected values and can raise events.
  • An alert about a data source that came back while the on-site agent restarted no longer stays open.
mirox-agents 3.1.337 – 3.1.345mirox 2.15.261 – 2.15.273
AgentImprovements and fixesAlerts & events

An inverter that sends nothing now reads as "Inverter not communicating" rather than as an outage. The alert for failed components now follows them as they drop out and come back, with a notification at the start and on recovery.

  • An inverter that sends nothing, and the combiner boxes behind it, now read as "Inverter not communicating" rather than as an outage.
  • The alert for failed components now follows them as they drop out and come back, with a notification at the start and on recovery.
  • On a plant's "Activity" page, an inverter or combiner box that keeps producing far below its expected model now gets its own event.
  • A battery with a power converter now delivers its data to the plant's battery views.
mirox-agents 3.1.322 – 3.1.333mirox 2.15.243 – 2.15.252
AgentImprovements and fixesSolar equipment

The string analysis now runs by itself, once a week and every night through a plant's first 30 days.

  • An alert for a device that stopped sending data now closes once the device is back.
  • Expected values now come from a flat-mounted irradiation sensor where a plant has one, and per inverter orientation where a plant faces several directions.
  • At plants with many strings, the string analysis again measures a full 30 days, so a string that sent nothing reads as having no data.
mirox 2.15.235 – 2.15.242mirox-agents 3.1.314 – 3.1.320
AgentImprovements and fixesAlerts & events

A component that has gone quiet is now reported on the same day, instead of the day after.

  • A component is reported roughly an hour after it stops sending data in daylight, instead of a day later.
  • An inverter whose strings were entered by hand and confirmed is now watched for outages, which it was not before.
  • A quiet stretch never counts towards an outage while the plant's irradiation is unknown, at night for example.
mirox-agents 3.1.305 – 3.1.306
AgentFeatureMajorBattery storage

A FREQCON BESS FQ battery storage system can now be added as a logger

A FREQCON BESS FQ battery storage system can now be added to a plant as a data logger, and each cabinet's state of charge, DC power, charge and discharge energy, and cell voltages and temperatures are then read. Plants receive this with their next agent update.

mirox-agents 3.1.298 – 3.1.304mirox 2.15.214 – 2.15.224
Read more in the documentationData loggers
AgentImprovements and fixesData collection

A device a data logger lists but has never measured now appears among the plant's components. Where a Solar-Log logger's daily totals are unreadable, daily energy is recovered from the devices' own readings.

  • A Solar-Log feed-in meter now appears in the plant's components even while it is still holding back its energy readings.
  • The single alert for components that stopped producing now arrives after 30 minutes instead of an hour.
mirox-agents 3.1.298 – 3.1.304
Read more in the documentationComponents
AgentFixMajorProduction & yield

Expected production at capped plants no longer reads too low

The expected-production curve read too low at plants whose output is capped, sitting well below the cap on bright days. It now follows the cap itself, and expected production on a bright day matches what the plant is allowed to deliver. Plants receive this with their next agent update.

mirox-agents 3.1.278 – 3.1.296mirox 2.15.198 – 2.15.213
AgentFeatureMajorData collection

A Solar-Log data logger can now be added with only its address

A Solar-Log data logger can now be added like any other, with only its address and, where the logger has one, its user password, after which every inverter, meter and sensor it lists is read, whatever its make.

mirox 2.15.190 – 2.15.197mirox-agents 3.1.259 – 3.1.276
Read more in the documentationData loggers
AgentFeatureMajorData collection

A new data logger now fills in the history it still holds

When a Solar-Log data logger or a Janitza meter is added, the devices behind it that are new to Mirox bring in the readings they still hold, up to two years back. This happens once, in the background, and plants receive it with their next agent update.

mirox 2.15.190 – 2.15.197mirox-agents 3.1.259 – 3.1.276
Read more in the documentationData loggers
AgentImprovements and fixesProduction & yield

An inverter whose energy counter stalls no longer lowers a Fronius plant's energy, and editing a data logger no longer splits other loggers' inverter history.

  • At Fronius plants, an inverter whose lifetime energy total stops advancing no longer lowers the plant's energy, its production being worked out from its power.
  • Adding or editing a data logger no longer causes another logger's Huawei or Sungrow inverters to appear as new components with their history split.
mirox 2.15.190 – 2.15.197mirox-agents 3.1.259 – 3.1.276
AgentFixMajorSolar equipment

The string analysis now gives a result for nearly every string

The string analysis now gives nearly every string a result, measured on the plant's clearest days, instead of only a handful. Strings on combiner boxes that measure current per input are no longer reported as unmeasurable, and plants receive this with their next agent update.

mirox-agents 3.1.257
AgentFeatureMajorCurtailment & grid limits

A Zebotec park controller now shows its power limits

A Zebotec PVPC park controller now shows the plant's active-power setpoints — the limit from the grid operator, the limit from the direct marketer, and the one the controller is acting on — each in percent of the plant's nameplate power. Plants receive this with their next agent update.

mirox-agents 3.1.250 – 3.1.256
AgentImprovements and fixesSolar equipment

String analysis is available again at plants that run under a standing power limit.

  • At plants on sloping ground, the direction strings face is now worked out correctly instead of reading too far east.
  • At plants under a standing grid or marketer power limit, string analysis is available again instead of a whole day counted as curtailed.
mirox 2.15.176 – 2.15.184mirox-agents 3.1.250 – 3.1.256
AgentFeatureMajorCurtailment & grid limits

A Wattkraft Parkcontrol park controller now needs only its address

A Wattkraft Parkcontrol park controller is now read from its address alone, without a login, delivering the active-power setpoints of the grid operator and the direct marketer, which of them is in force, and whether the link to the direct marketer is up.

mirox-agents 3.1.243
AgentFixData collection

Unreachable Huawei inverters no longer report zero production

Huawei plants no longer show production dropping to zero when the data logger cannot reach an inverter. An unreachable inverter is now left out instead of being recorded as zero, and the plant's power is worked out from the inverters that did answer.

mirox-agents 3.1.233 – 3.1.237
AgentImprovements and fixesSolar equipment

The string analysis now runs in more situations: without a panel datasheet, on cloudy days, and where a string's orientation cannot be measured.

  • Without a panel datasheet the analysis still finds each string's wiring, connections and orientation, and only the peak power is missing.
  • A string whose own orientation cannot be measured now takes the orientation of its inverter, instead of being left out.
  • When there are too few clear days, cloudy days now help work out orientation, counting for less than a clear day.
  • A day when the plant stopped sending for an hour is still measured, instead of being set aside as overcast.
  • If no strings are set up for the inverters, the analysis now says so instead of failing with an error.
  • Expected production now follows the configured strings even when some lack a peak power or an orientation, instead of the plant's peak power alone.
mirox-agents 3.1.233 – 3.1.237
AgentFeatureAlerts & events

An irradiation sensor that stops measuring is now reported

An irradiation sensor is now flagged when it reads zero while a neighbouring sensor or the plant's own production shows the sun is up. A confirmed defect also sends a notification.

mirox-agents 3.1.227 – 3.1.232mirox 2.15.166 – 2.15.172
AgentImprovements and fixesData collection

Combiner boxes, irradiation sensors and feed-in meters now name the data logger they are read from. An older device reached through remote access no longer asks for a login over and over.

  • Combiner boxes, irradiation sensors and feed-in meters now show the data logger they are read from.
  • An older device's own web page, reached through remote access, no longer asks for a login over and over.
  • Adding a data logger now reports when its test read keeps failing — a missing login, for example — instead of showing nothing.
mirox-agents 3.1.227 – 3.1.232mirox 2.15.166 – 2.15.172
AgentFeatureMajorData collection

An SMA Sunny Central plant now comes in from one address

An SMA Sunny Central plant can now be added with "SMA Sunny Central" as the data logger and the address of its SC-COM gateway, behind which its inverter, the string monitor control and every string monitor are found. Plants receive this with their next agent update.

mirox 2.15.160 – 2.15.165mirox-agents 3.1.220 – 3.1.226
AgentImprovements and fixesSolar equipment

Huawei inverters now report their insulation resistance.

  • A combiner box now shows the serial number the on-site agent read from it.
  • The satellite irradiation figures in settlement events, which had stopped at 2026-07-31, update again on their own.
mirox-agents 3.1.220 – 3.1.226
Read more in the documentationMarket
AgentFixMajorCurtailment & grid limits

Flat-rate settlement now deducts the direct marketer's share

In a "Redispatch settlement" event, the lost energy worked out by the flat-rate (pauschal) method previously counted quarter-hours the direct marketer had curtailed at the same time. For months from July 2026 the figure is net of that share and decreases where the two overlapped, while earlier months keep the gross figure. Plants receive this with their next agent update.

mirox 2.15.144 – 2.15.151mirox-agents 3.1.214
Read more in the documentationMarket
AgentFixMajorProduction & yield

Curtailed minutes no longer count against the performance ratio

The performance ratio read too low at plants that were curtailed, and the expected production scaled from it was too low as well. Both are correct from this release, which plants receive with their next agent update. Plants receive this with their next agent update.

mirox-agents 3.1.214
AgentFixAlerts & events

A plant going offline now raises a single event

A plant that goes offline now raises one alert instead of two or none, and the alert closes only once the whole plant is reachable again. Alerts for devices that drop out in the same moment are held back, and plants receive this with their next agent update.

mirox-agents 3.1.208 – 3.1.212
AgentImprovements and fixesData collection

Grid meter readings taken through a Phoenix Contact controller no longer arrive with the feed-in direction reversed.

  • A Phoenix Contact controller now works out by itself which direction the grid meter counts, and shows no grid values until it is sure.
  • "Grid sign convention" in the controller's settings sets the direction by hand when the automatic check cannot decide.
  • Settlement events now also carry the lost energy worked out by the flat-rate (pauschal) method, beside the figures from each irradiation source.
  • Curtailments back to January 2025 are now settled, the reference day for months before July 2026 being the last suitable day before the curtailment.
  • A settlement event now names an irradiation source left out and why, and a morning gap in its readings no longer leaves the afternoon unsettled.
  • Expected production now follows each string's own orientation and size when the plant's components state them all, instead of one plant-wide orientation.
mirox-agents 3.1.203 – 3.1.207mirox 2.15.130 – 2.15.133
Read more in the documentationMarket
AgentFeatureCurtailment & grid limits

Direct-marketer curtailments now get a "Marketer settlement" event

For each curtailment measure by the direct marketer, the lost energy is now recorded as a "Marketer settlement" event on the plant's "Activity" page, beside the "Redispatch settlement" events of grid-operator curtailments. The measure's own day can serve as its reference day, since only grid-operator curtailments disqualify a day. Plants receive this with their next agent update.

mirox 2.15.126 – 2.15.129
Read more in the documentationMarket